1、 ( )是企業(yè)信息系統(tǒng)的重要目標(biāo)。


該工程的計算工期為(1)周。按此工期,整個工程至少需要(2)人。
(1)A.7
B. 8
C. 10
D. 13
(2)A. 9
B. 10
C. 12
D. 14
信管網(wǎng)參考答案:A、B
查看解析:http://m.conferencecallsmadeeasy.com/st/403.html
60、 某公司準(zhǔn)備將新招聘的4名銷售員分配到下屬3個銷售點(diǎn)甲、乙和丙。各銷售點(diǎn)增加若干名銷售員后可增加的月銷售額如下表:

根據(jù)此表,只要人員分配適當(dāng),公司每月最多可以增加銷售額( )千元。
A. 43
B. 47
C. 48
D. 49
信管網(wǎng)參考答案:C
查看解析:http://m.conferencecallsmadeeasy.com/st/404.html
61、 某車間需要用一臺車床和一臺銑床加工A、B、C、D 四個零件。每個零件都需要先用車床加工,再用銑床加工。車床和銑床加工每個零件所需的工時(包括加工前的準(zhǔn)備時間以及加工后的處理時間)如下表。

若以 A、B、C、D 零件順序安排加工,則共需 29 小時。適當(dāng)調(diào)整零件加工順序,可產(chǎn)生不同實(shí)施方案,在各種實(shí)施方案中,完成四個零件加工至少共需 ( )小時。
A. 25
B. 26
C. 27
D. 28
信管網(wǎng)參考答案:B
查看解析:http://m.conferencecallsmadeeasy.com/st/405.html
62、 制造某種產(chǎn)品需要四道工序,每道工序可選用多種方法。下圖列出了制造這種產(chǎn)品各道工序可選用的不同方法:從節(jié)點(diǎn)1開始,連續(xù)經(jīng)過4條線段(表示4道工序所 選用的方法),組成一條線路,直到節(jié)點(diǎn)12結(jié)束。每條線段上標(biāo)記的數(shù)字表示利用相應(yīng)方法每件產(chǎn)品可以獲得的利潤(元)。企業(yè)為了獲取最大利潤,需要找出從 節(jié)點(diǎn)1到節(jié)點(diǎn)12的一條線路,使其對應(yīng)的各道工序的利潤之和達(dá)到最大。利用運(yùn)籌方法計算后可知,制造每件產(chǎn)品可以獲得的最大利潤是( )元。

A. 28
B. 31
C. 33
D. 34
信管網(wǎng)參考答案:C
查看解析:http://m.conferencecallsmadeeasy.com/st/406.html
63、 Define Activities is the process of identifying the specific actions to be performed to produce the ( ).
A. project elements
B. work drafts
C. work package
D. project deliverables
信管網(wǎng)參考答案:D
查看解析:http://m.conferencecallsmadeeasy.com/st/407.html
64、 Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for ( ), scheduling, executing, and monitoring and controlling the project work.
A. reviewing
B. estimating
C. auditing
D. expecting
信管網(wǎng)參考答案:B
查看解析:http://m.conferencecallsmadeeasy.com/st/408.html
65、 The Estimate Activity Resource process is closely coordinated with the( )process.
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
信管網(wǎng)參考答案:A
查看解析:http://m.conferencecallsmadeeasy.com/st/409.html
66、 Estimating activity durations uses information on activity scope of ( ), required resource types, estimated resource quantities, and resource calendars.
A. milestone
B. baseline
C. quality
D. work
信管網(wǎng)參考答案:D
查看解析:http://m.conferencecallsmadeeasy.com/st/410.html
67、 Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress.
A. analyze
B. track
C. level
D. extend
信管網(wǎng)參考答案:B
查看解析:http://m.conferencecallsmadeeasy.com/st/411.html
掃碼關(guān)注公眾號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
| 發(fā)表評論 查看完整評論 | |